Site Development



May Update 4/5/2017

BMFA Buckminster May Blog The months have rolled by pretty quickly but  it feels like we have made fairly spectacular progress since we took possession of the site in November and the main contractor commenced…


April 2017 Site Development Update

Site Progress Following positive progress from the main contractor the National Centre will be open for business on the 8th of May (as opposed to the 1st as previously advertised) This slight delay is to…



March 2017 Site Development Update

March 2017 Work on site has continued to progress in line with the schedules set out in the initial programme of works which completes the contractors phase 1 works on or around the 28th of…


February 2017 Site Development Update

February 2017 Work on site has continued to progress well and largely in accordance with the schedules set out in the initial programme of works. Weather of course plays a part and to date three…


January 2017 Site Development Update

January 2017 Work really kicked into gear on site during the second week of January (after the traditional construction industry long Christmas break) The Principal Contractor (Front Row Construction) moved machinery on to site, initially…



November 2016 Site Development Update

November 2016 Much has been happening over the previous months but the signing of the lease sets the scene for the ‘serious work’ to commence in accordance with the initial project plan. Lease document signed…